Sector Headquarters, Warsak
Project Title: Design and construction of 10 buildings in the Sector Headquarter
Compound of the Frontier Corps Peshawar along with all furniture
and fixtures
Client: Lockheed Martin Readiness & Stability Operations, USA
End User: Pakistan Army Frontier Corp, NWFP
Consultant: Lockheed/CENTCOM-appointed consultant
Period: 2008 - 2010
Astral Scope: Prime Contractor; Complete Design & Build
Brief Description: Construction (complete design and build responsibility) of a Sector Headquarters Compound facility comprising of 10 buildings on site complete with all road works and utilities (Including grid and generator power, water source, sewage treatment etc.) with ancillary works such as boundary walls, gates and other AT/FP measures and facility-grade with fire prevention systems for the Pakistan Army Frontier Corp (FC) at Warsak, NWFP/FATA. Project value US$ 5.8 m.